Timeline
Traffic Closure and Construction starting 10/31/2011
Sunnyside
- Detours Remain in place for 8 weeks
- Demolition of the Steel Bridge
Berteau
- Detours Remain in place for 10 weeks
- Install retention barriers
Grace
- Install temporary bridge support
- Install safety handrail
- Detours will be set up around 11-3-11
- Crane will be moved from Berteau to Grace around 11-4-11
Between Lawrence & Winnemac
- Signal Bungalow retaining wall structure
Foster & Balmoral
- Install temporary bridge support
Short Term:
Bridge construction has started on Sunnyside, Berteau and Grace.
Medium Term:
The Sunnyside, Berteau and Grace bridges are expected to be completed by spring 2012.